May 2008: Flows at or above 1500 cfs at the put-in below Boyle Powerhouse (Spring Island Put-in) should occur every day during typical
boating hours (8:00 AM – 5:00 PM), 7 days a week.
June 1 – September 14; Non-holiday periods (Monday, Tuesday, Thursday, Friday, Saturday, and Sunday,): The J.C. Boyle Generator unit start time will be 8:00 a.m. for these days. Flows of 1200 cfs or greater are typically achieved
at the powerhouse, approximately three hours after the indicated generation unit start time. An additional 150-300 cfs of
base flow occurs in the JC Boyle bypass reach, between the dam and the put-in. It is recommended that all boating parties
check the BLM staff gauge at the put-in to verify actual flow. Recreational users should recognize that the cfs values listed
in the Hourly Estimated Flows Table are an average for the hour listed (i.e., the value for 11:00 is an average of the flows
occurring between 10:00 and 11:00). Therefore, when ramping is in progress, actual turbine flow on the hour indicated may
be approximately 150-300 cfs higher than the value shown.
June 1– September 14; Non-holiday periods (Wednesday): Open day as needed. This is PacifiCorp's day to correct reservoir position, if needed, so that recreation and power commitments
can be preserved for the balance of the week. PacifiCorp reserves the right to operate the project later in the day or as
necessary. PacifiCorp recommends all river users check the
water release schedule
to verify flows for these days.
4th of July Holiday (July 4-6): Raftable flows (1500 cfs at put-in) by 10:00 a.m. forecasted for all days. PacifiCorp recommends all river users check the water release schedule
daily, to verify flows and release times.
Labor Day Weekend Aug 30-Sept 1: (Saturday - Monday): Raftable flows (1500 cfs at the put-in) by 10:00 a.m. forecasted for all three days. PacifiCorp recommends
all river users check the
water release schedule
daily, to verify flows and release times.
Summer 2008 J.C. Boyle Maintenance Outage Schedule: There are currently no planned maintenance outages at the J.C. Boyle project for July and August 2008. However, there
is always the possibility of a mechanical failure causing unplanned outages. Any unplanned outages at J.C. Boyle could impact
the rafting schedule. Check the
water release schedule
daily, to see if unplanned outages have any effect on rafting.
The intent in providing the above information is to provide raft-able flows, as listed. However, if difficulties arise in
the power supply situation, PacifiCorp reserves the right to operate the project later in the day or as necessary. PacifiCorp
recommends all river users check the
water release schedule
daily, to verify flows and release times.
If you have questions or comments about the information provided herein, contact Mike Blum, Klamath Project Production Manager,
(530) 459-2003.
For more information on this and other rivers, call our Public Service recording at:(800) 547-1501.
|