Powerdale


2006 Flood on the Hood River

PacifiCorp had planned to continue operating Powerdale until beginning the decommissioning process in April 2010. However, on Nov. 7, 2006, a flood and the resulting debris flow damaged the facility, including complete destruction of key sections of the flowline between the dam and the powerhouse. One section of the flowline collapsed into Hood River and another section collapsed in place. There also was flooding of the powerhouse and substation, and a significant amount of sediment ended up at the diversion dam intake and powerhouse tailrace. 

Because of the potential that high levels of sediment in the flood flows would cause damage, PacifiCorp had shut down project operations before the flood occurred. Immediately after flood waters receded, PacifiCorp began stabilizing the project. This work, which was completed in February 2007, included measures to safeguard the public. The diversion dam, which previously had served as a recreational facility, became off limits. Public access to areas around collapsed sections of flowline and the powerhouse was also restricted. Hazardous materials were removed from the shop and chemical storage building. The section of steel flowline was removed from Hood River, as were sections in imminent danger of collapse. Both collapsed sections of wood-stave flowline and those in danger of collapse were removed. Security bulkheads were installed on all open flowline sections. 
 
Given the extent of the November 2006 flood damage, PacifiCorp asked FERC early in 2007 for permission to immediately cease power generation. Decommissioning was to begin in only three years, the cost of returning the project to operation would be more than $4 million, and PacifiCorp’s other facilities could provide the 47,000 megawatt hours predicted to be lost at Powerdale, so FERC granted permission to cease generation on Feb. 8, 2007. PacifiCorp is still required to complete decommissioning by 2012, but no longer is required by FERC to generate power at the facility. 

Project Contacts

Todd Olson
Program Manager
825 NE Multnomah, Suite 1500
Portland, OR 97232
(503) 813-6657
todd.olson@pacificorp.com

Eric Hansen
Project Manager
825 NE Multnomah, Suite 1500
Portland, OR 97232
(503) 813-5013
eric.hansen@pacificorp.com

Arianne Poindexter
Project Coordinator
825 NE Multnomah, Suite 1500
Portland, OR 97232
(503) 813-5513
arianne.poindexter
@pacificorp.com