This solar request for proposal (RFP) (2013S Solar RFP) seeks acquisition of solar resources to meet the Company’s remaining Oregon solar capacity mandate goal of 6.7 MWAC. Bids must comply with specific RFP criteria including; meeting company solar specifications, individual project capacity greater than 500 kWAC and up to 5.0 MWAC, commercial operation date on or before December 31, 2014, fixed price power purchase agreement or asset purchase and sale agreement only, and delivery to PacifiCorp’s system on firm basis.

Information for the Request For Proposal (RFP) process is outlined below. More information will be made available as it is released. For questions or more information, please send an email to RFPSolar@PacifiCorp.com.

Schedule

Event Estimated Timeline
2013S issued April 30, 2013
PDF Bidder/stakeholder meeting May 13, 2013
Responses due June 11, 2013
Bid evaluation completed July 16, 2013
Shortlist selection July 19, 2013
Best and final pricing update by shortlist August 6, 2013
Bidder negotiations completed September 30, 2013
Final selection October 4, 2013
Project commercial operation date December 31, 2014