North Umpqua River flows

The flows represented by this gage station are in the North Umpqua River's Wild and Scenic Reach downstream of the North Umpqua Hydroelectric Project and Boulder Creek (a wilderness stream).

Real-Time flow data for this site is available from gage station 14316500 funded by PacifiCorp and managed by the USGS.

Forecasted flows for a nearby tributary, Steamboat Creek, are provided by NOAA's Northwest River Forecast Center.

Tentative 2024 schedule of planned waterway maintenance which may affect flow in bypass reaches or trigger fish salvage activity at the North Umpqua Hydroelectric Project. Maintenance has been planned to occur during the Settlement Agreement preferred periods to the greatest extent possible. Dates are tentative and can change without notice due to weather, access, equipment, personnel, maintenance progress, and other issues. The dates listed are the approximate date of canal or powerhouse shutdown, but ramping and flow changes may impact adjacent days as well. During some outages it may be possible to keep “fish flow” in the waterway, which means sufficient flow to keep fish alive, generally 2-20 cfs depending on the waterway, season, and weather. Note also that high natural flows and unplanned shutdowns for emergency responses and brief maintenance events may occur at any time without advance notice. For details contact Rich Grost, PacifiCorp, 541-498-2617. For details contact Rich Grost, PacifiCorp, 541-498-2617. Version 7: 9-6-24.

        

     
     

Waterway

Approximate dates of shutdown

Bypass reach flow affected?

Date of fish salvage

Fish liberated to

Notes

 

Lemolo 1 

None planned

yes

       

Lemolo 2

2/16 – 10/1 
(and into 2025)

yes

10/1-31

na

Increased bypass flow due to canal flow limitation to support flume and trestle maintenance

 

Lemolo 2

10/1 – 12/31 
(and into 2025)

yes

na

Lemolo Lake, Toketee Lake

Fish salvage takes 4-5 days for canal, sag pipe, tailrace; Lemolo Lake is preferred liberation site

 

Clearwater 1

6/12

yes

na

na

Fish flow retained in canal for 1-day outage

 

Clearwater 2

4/8 – 26
6/13
 

Yes yes

4/9 na

 

Clearwater 2 4bay na

Completed
Fish flow retained in canal for 1-day outage

Toketee (one turbine)

7/15 – 8/2
(substation work)
11/6 – 11/22
(TIV install)

If inflows exceed 900 cfs

na

na

Toketee Unit 2 rebuild; Units 1 and 3 remain operating

 

Toketee (two turbines)

No longer planned this year

If inflows exceed 500 cfs

na

na

Toketee Unit 3 rebuild; Unit 1 remains online

 

Toketee (all three turbines)

7/15 – 8/2

(substation work)
11/6 – 11/22

(TIV install)

yes

na

na

Three Unit maintenance; no salvage as fish screen precludes most fish from the unsalvageable tunnel which drains to river when dewatered; requires filling Toketee Lake to spill bypass reach flows

 

Fish Creek

5/31 – 12/31

yes

na

na

Fish screen precludes fish from canal, diversion reduced to <1 cfs to maintain forebay above 3020 ft MSL, canal flow reduced due to capacity limitation at Flume 7 until repairs completed.

 

Fish Creek

When natural
inflow <130 cfs (~July-Oct)

no

na

na

Fish screen precludes fish from canal, diversion generally shut down in summer and fall

 

Slide Creek

None planned

 

 

 

 

 

Soda Springs

3/25 – 4/4

yes

na

na

Fish screen precludes fish, penstock drains to river

 

Soda Springs fish passage facility

8/12 - 30

no

na

adjacent waters (brown trout to Lemolo Lake if time allows)

No dewatering planned - focus on above-water maintenance of fish screen and brief semi- dewatered maintenance of fish return system and FEB, no fish salvage needed