RFP 2017S Solar RFP Main Document
RFP 2017S Solar RFP Document Map
RFP 2017S App A Solar Technical Specification
RFP 2017S App A-1 Overview of Appendices
RFP 2017S App A-2 Interconnection Agreement
RFP 2017S App A-3 Permit Matrix
RFP 2017S App A-5 Project Single Line Drawings and Layouts
RFP 2017S App A-6 Division of Responsibilities
RFP 2017S App A-8 Performance Summary Report
RFP 2017S App A-9 Solar Product Data Equipment Supply Matrix
RFP 2017S App A-10 Plant Performance Guarantee Solar
RFP 2017S App C-1 Bid Summary PPA (Updated 12/4/17)
RFP 2017S Solar Appendices A-O
A-7.01 Attachment 1A Project Document Formatting and Requirements
A-7.02 Attachment 1B Document Deliverables
A-7.03 Computer-Aided Design Drafting Standards 9A
A-7.04.1 PXS02-S02A Substation Equipment-Collector Substation Main Power
A-7.04.02 ZS-102 Two-Winding Dist Transformer Inverter Step-Up Liquid-Immersed
A-7.05 EBU-SI-S04 Electrical-Equipment Insolating Oil
A-7.06 EBU-SI-S02 Wind Ice and Seismic Withstand
A-7.07 EBU-SI-S03 Contaminated Environment Protection
A-7.08 SP-TRF-INST Transformer Installation Procedure
A-7.09 Asset Management Form 006F
A-7.11 Part 6B 6 Substation Grounding
A-7.12 GEN-ENG-RELAY-0001 Protective Relaying Requirements for New Plants
A-7.13 GEN-ENG-RELAY-0002 Arc Flash Requirements for New Plants rev 5
A-7.14 GEN-ENG-RELAY-0003 CT and PT testing procedure
A-7.15 GEN-ENG-RELAY-1003 PRC 005
A-7.16 Relay Testing and Commissioning Checklist
A-7.17 Relay Installation Procedure GPCP-EQPMNT-INST
A-7.18 Current Transformer Installation Procedure GPCP-CT-INST
A-7.19 Current Transformer GPCF-CT-INST FORM
A-7.20 SG001Substation High-Voltage Signs
A-7.21 Specification for Substation Equipment Installation Testing Commissioning
A-7.22 SV002 Bird and Animal Protection-General Installation Instructions
A-7.23 SV251 Bird and Animal Protection for Miscellaneous Equipment