The PacifiCorp 2025 Integrated Resource Plan and PacifiCorp’s 2023 Clean Energy Plan established an action item to conduct a small-scale renewable request for proposals to acquire by 2030 small-scale renewable resource capacity sufficient to meet requirements of Oregon House Bill 2021 (OR HB2021), Section 37. This RFP is also a first step in addressing a non-wire solution for grid needs per UM2005. Based on current estimated projections, PacifiCorp is looking to procure as much as 320 megawatts of capacity from small-scale resources that meet the requirements set forth in OR HB2021.
Accordingly, the 2025 Oregon Small-Scale Renewable RFP (2025 OR SSR RFP) will consider cost-competitive bids for resources with the following characteristics:
The 2025 OR SSR RFP will accept and evaluate bids for small-scale resources with a guaranteed commercial operation date on or before December 31, 2029. Review the RFP Main Document below for additional information.
The following notices have been emailed to PacifiCorp’s 2025 OR SSR RFP email distribution list:
For questions or to be added to the list, please contact 2025SSR_RFP@pacificorp.com
The Q&A period for the RFP is reopened. The last day for bidder questions to PacifiCorp is November 19, 2025. An updated list of questions and answers posed by stakeholders to the 2025 OR SSR RFP email address, through November 19, 2025, will be posted here.
Previous questions and answers through June 24, 2025, from the original issuance of the 2025 OR SSR RFP are posted here: Previous Questions and Answers
The proposed 2025 OR SSR RFP schedule is shown below and subject to change. PacifiCorp will provide further updates on the status and schedule of its 2025 OR SSR RFP (including webinar information for publicly available workshops) on this webpage as they become available.
EVENT | DATE |
RFP issued to market and publicized |
7/25/2025 |
Bidder workshop |
7/30/2025 |
Last day for Bidder questions to PacifiCorp |
11/19/2025 |
Bid submissions due |
12/17/2025 |
Bid evaluations complete |
1/14/2026 |
RFP final shortlist complete |
1/28/2026 |
Contracts finalized and executed |
6/30/2026 |
Guaranteed commercial operation date (GCOD) |
12/31/2029 |
PacifiCorp hosted a second bidder workshop for the reissuance of the 2025 SSR RFP on July 30, 2025. This workshop covered the RFP structure, deliverables, schedule, requirements and changes from the original issuance of the RFP. The presentation and a recording of the workshop are below:
PacifiCorp hosted a workshop for interested stakeholders and bidders to discuss the 2025 OR SSR RFP via a webinar on May 6, 2025. The presentation and a recording of the workshop are below:
Watch the recording of the workshop
Any questions on the 2025 OR SSR RFP or related documents can be sent to 2025SSR_RFP@pacificorp.com