This project will consist of rebuilding and reconductoring existing high voltage transmission line infrastructure from Idaho to Utah. The project involves the following substations: Populus, Bridgerland, Ben Lomond, Threemile Knoll, Soda, Grace, Oneida, and Treasureton. The project will be completed in two phases. The first phase will focus on the 67-mile, 345 kV reconductor that anticipates completion by the end of 2028. The second part of the project will focus on the 40-mile, 138 kV rebuild that anticipates completion by the end of 2030. This project will increase overall system reliability while improving capacity.
The purpose and need for the Populus to Terminal Segment B project rebuild is to ensure the transmission system is reliable. Due to increased electrical demand, the existing transmission infrastructure will not have sufficient capacity to reliably serve future load requirements. This reconductoring and rebuild will provide additional capacity to help in serving load growth while increasing overall system reliability.
The project will feature the following components:
PROJECT FEATURE |
138 kv |
345 kv |
Voltage (volts) |
138 kV |
345 kV |
Line length (miles) |
40 |
67 |
Type of structure |
Monopole |
Latice Towers/Monopole |
Type of structure material |
Wood or Steel |
Steel (Self-Supporting) |
Structure height (above grade) (feet) |
80-100 |
125-165 |
Span length (feet) |
600-800 |
800-200 |
ROW Width (typical) |
85 |
150 |
The affected entities in this project include the Bureau of Land Management, the Bureau of Reclamation, as well as local jurisdictions that include:
Utah |
Idaho |
Cache County |
Franklin County |
Box Elder County |
Bannock County |
Cornish Town |
Caribou County |
Deweyville Town |
Weston City |
Honeyville City |
|
The link to the project map indicates the route and the two phases through which work will be completed.
Segment B Honeyville to Populus and Threemile Knoll - Project Map
345kV Rebuild (Populus - Honeyville) |
138kV Rebuild (Threemile Knoll - Treasureton) |
|
Survey and Right-Of-Way: June 2024 – March 2027 |
Survey and Right-Of-Way: June 2024 – Jan 2029 |
|
Permitting: Jan 2025 – Jan 2027 |
Permitting: Jan 2025 – Mar 2029 |
|
Construction: Jan 2027 – Oct 2028 |
Construction: Jan 2029 – Oct 2030 |
|
In-service: Q4 2028 |
In-service: Q4 2030 |
After providing a project introduction to local jurisdictions, PacifiCorp will provide opportunities to inform the public of the project and will answer questions. Throughout the permitting process, it is anticipated that local jurisdictions along the project route may require additional public outreach and engagement. Information about all open house meetings and engagement opportunities will be noticed and can also be found on this page.
More information will be made available soon.
Requests for additional information on the Populus to Terminal Segment B project may be directed to pmopac@PacifiCorp.com. Please include the word “Segment B” in the subject line and provide your contact information and preferred contact method in the body of the message.