The 2025 Integrated Resource Plan (IRP) established an action item to initiate request for proposals (RFP) to procure resources for its Washington customers that are aligned with the 2025 IRP preferred portfolio and that can achieve commercial operation by the end of December 2029. The 2025 IRP estimates a need for as much as 900 megawatts of generation resources primarily to satisfy Washington Clean Energy Transformation Act (CETA) compliance and 1,385 megawatts of storage to primarily satisfy Western Resource Adequacy Program (WRAP) compliance for capacity.
PacifiCorp’s 2025 Washington Situs RFP is seeking competitively priced resources that are agnostic to both duration and technology type. PacifiCorp’s 2025 Washington Situs Request for Proposals will consider power purchase agreement and energy storage agreement bids. PacifiCorp is not submitting any self-build (benchmark) resources in its 2025 Washington Situs Request for Proposals.
For questions or to be added to the 2025 Washington Situs RFP distribution list, please contact us at: 2025WASitusRFP@PacifiCorp.com.
An updated list of questions and answers posed by stakeholders to the 2025 Washington Situs RFP email address, through September 12, 2025 are posted here: Questions and Answers
Questions should be submitted to 2025WASitusRFP@PacifiCorp.com. Interested parties are encouraged to monitor this site for responses to additional questions.
See the RFP main document with instructions and supporting appendices.
PacifiCorp hosted a workshop for interested stakeholders and bidders to discuss the 2025 Washington Situs RFP via a webinar on September 17, 2025. The presentation and a recording of the workshop are below:
Watch the recording of the workshop
Questions for PacifiCorp: Any questions or comments by interested parties regarding the 2025 Washington Situs RFP can be sent via email to PacifiCorp to 2025WASitusRFP@PacifiCorp.com. Interested parties are encouraged to monitor this site for responses to subsequently submitted additional questions.
This RFP schedule is indicative and remains subject to change. Interested parties are encouraged to monitor this website for subsequent schedule updates and information regarding bidder workshop participation.
Milestone |
Date |
2025 WA Situs RFP issued to market |
9/2/2025 |
Bidder Workshop |
9/17/2025 |
Last day for bidder questions to PacifiCorp |
9/30/2025 |
Bid submissions due with pricing |
10/7/2025 |
Bid evaluations and ranking complete |
2/12/2026 |
Contracts finalized and executed |
3/30/2026 |
Guaranteed commercial operations date (COD) |
12/31/2029 |
Questions about the 2025 WA Situs RFP and/or requests to be placed on the stakeholder distribution list for this 2025 Washington Situs RFP may be directed to 2025WASitusRFP@PacifiCorp.com.